Diary of an Extension Part 6


Day 35 - windows fitted and the shell secure.  
   Day 40 -  Plumbing in and the upstairs floor completed. 

  Day 42 - Holes in the walls as old to new are joined. The new downstairs staircase is in although more work has to be done to finish it. 
  Day 43 -  The new staircase upstairs is fitted as is the shower tray and the stud walls separating the shower room from the new bedroom. 

Day 45 - Plastering mostly finished. Rooms starting to look like rooms  
  Day 47 -  Plaster has dried. New central heating radiators fitted to the system.

 


 